Persistent leaks threatened this high-traffic underground parking. EURAS® Gel Type B was injected under pressure—sealing cracks without disruption.
Private Developer / Facility Management Company
New Belgrade, Serbia
Chronic leaks threatened this critical water treatment facility. EURAS® Gel Type B was injected under pressure—permanently sealing slabs and galleries.
2011-2012
Episkopi Desalination Plant Operator
Episkopi, Cyprus
Chronic leaks reduced capacity in this potable water reservoir. EURAS® Gel Type B was injected under high pressure—restoring integrity without excavation.
2002-2004
Wasserwerk Usingen
Usingen, Hesse, Germany
Chronic leaks threatened this high-value residential basement. EURAS® Gel Type B was injected under pressure—permanently sealing cracks without demolition.
2016
King’s Court Residential Complex
Belgrade, Serbia
In an Alpine hydropower station suffering chronic leaks, EURAS® Gel Type B was injected under high pressure—sealing joints and cracks permanently.
2015
Elektrizitätswerk Obwalden AG
Melchsee-Frutt, Obwalden, Switzerland
Facing chronic leaks in a high-traffic railway tunnel, our team applied EURAS® Gel Type B by high-pressure injection—creating a lasting waterproof barrier.
2010
DB Netz AG (German Railway Infrastructure)
Cochem, Rhineland-Palatinate, Germany
Active leaks around cooling galleries and pipe penetrations threatened safety and compliance. EURAS® Gel Type B was injected under high pressure, creating a lasting watertight barrier.
2007
Uniper Kraftwerke GmbH
Kraftwerk Hamm-Uentrop, Germany
When active leaks threatened the valve chamber of this hydropower plant, the EURAS® team responded with high-pressure injection of Gel Type B—sealing the structure in just 48 hours.
2011-2012
Elektroprivreda Srbije (EPS)
PAP Lisina – HE Vrla, Serbia
Facing widespread leaks in an underground garage near the sea, our team injected over 12,000 kg of EURAS® Gel Type B—sealing cracks and cavities permanently.
2013
Limassol Marina Ltd.
Marina Limassol, Cyprus
Persistent leaks under high reservoir pressure threatened dam safety. Using EURAS® Gel Type B, our team performed deep high-pressure injection—stopping leaks permanently without lowering water levels.
2016
Agence Nationale des Barrages et Transferts (ANBT)
Kissir Dam, Jijel, Algeria
When chronic leaks at the surge chamber–tunnel interface threatened performance, EURAS® Gel Type B was injected under high pressure to create a permanent waterproof barrier.
2014
DEM – Dravske Elektrarne Maribor
ČHE Avče, Slovenia
Persistent water leaks in the penstock galleries of this hydroelectric plant were compromising operations and structural safety. Traditional methods failed — until EURAS® Gel Type B was applied.
2014
ELEM – Elektrani na Severna Makedonija
HEC Sveta Petka, FYR Macedonia
A leaking expansion joint (S2–S3) in one of Serbia’s most critical hydroelectric plants was sealed without shutting down operations using EURAS® Gel Type B.
2012
EPS – Elektroprivreda Srbije
Hydroelectric Power Plant Đerdap 1, Serbia